Mega Project: Full cycle treatment plant + Two pipe networks for Bani Haroon & Kom villages

This project serves the needs for the local Bani Haroon and Kom ahmar villages in Bani Sweef. It is composed of two pump stations, 50 Kilometers of pipe network, and a sewerage treatment plant.

Funded by the USAID and Under the Supervision of the Egyptian Holding Company for Water and Wastewater.

This project is currently serving over 140,000 residents.

Project Status: Completed on time and is operating and managed by local government.

The contract value is $ 8.8M

At a Glance

Status Completed
Client Egyptian Holding for Water and Wastewater
Consultant Chemonics Egypt
Location Bani Sweef
Project Cost $8.8